(From The Times Picayune) When construction began in 2006 on the Jefferson Performing Arts Center, the price tag was $26.5 million and the contract called for completion in two years. In the ensuing five years, the cost has exploded by two thirds to $44.7 million, through a series of seven change orders. And the project, still unfinished, has attracted sharp criticism, most recently from the state legislative auditor who pointed out sloppy accounting, poor decision-making and lack of oversight.
Jefferson Performing Arts Center price soars – When construction began in 2006 on the Jefferson Performing Arts Center, the price tag was $26.5 million and the contract called for completion in two years.