The Metro Council’s chamber was crowded last December for the hearing on the city-parish’s $741 million budget. The public hearing went on for two hours.
But practically the only thing anyone wanted to talk about was a $19 million line item for a new River Center library. The library board previously had voted to tear down the current branch and build a larger, next-generation facility in its place.
The outsized controversy over the library board’s decision, which to a large extent pitted young professionals and city elites against older, more conservative residents, didn’t end that night. But the issue finally was settled once and for all last month. Maybe.
In 2005, when library officials were campaigning for renewal of their 11.1-mill property tax, their literature said about 90% of the money would be spent on operations and 10% on construction, including a new Main Library downtown, reflecting the position of the board at the time. The tax renewal passed easily.
But opponents of building a new Main Library downtown, citing a lack of parking and the distance from East Baton Rouge Parish’s residential population centers, among other factors, decried the plan and didn’t give up. In February 2007, Mayor Kip Holden came out in favor of keeping the main library on Goodwood Boulevard, but suggested downtown needed a better library than the one it had.
Thus the idea of a super-regional downtown library was born, a concept embraced passionately by its champions but never mentioned in the literature or approved by voters, as current library board member Stanford Bardwell points out. By his calculation, the new downtown library pushes construction spending to 12% of revenue.
“There was a camp that said, ‘If you build, it they will come,’” Bardwell says. “But we’re building the flagship, showcase library on Goodwood. That’s a downtown branch, that’s all. The proponents were seeing it as a junior main library.”
Bardwell favored remodeling the downtown library right up through a September 2010 board meeting, when a majority voted in favor of building a new facility. That vote was scrapped to allay complaints that it was not properly advertised.
Bardwell, knowing he was outnumbered in the October re-vote, dropped his opposition in exchange for assurances the library would have top-notch technology but not an underground parking garage, which he says could create legal liabilities.
It was that October vote that enabled the $19 million line item for the new library to find its way into Holden’s budget. After the extensive public hearing, seven of 12 Metro Council members voted to remove the item, one vote less than the required two-thirds majority to alter the mayor’s budget.
During summer 2011, architect Trey Trahan, who competed for the downtown library design contract but was not selected, claimed information meant to damage his reputation was circulated to the selection committee. The design of a European building said to be similar to Trahan’s design for the library supposedly was given to committee members in an attempt to imply Trahan’s design was not original. An investigation by the parish attorney’s office found that only two committee members saw the design, and that the release of such information had no bearing on the final vote.
Prior to the Metro Council’s scheduled Sept. 28 meeting, five members had put forward an agenda item urging the library board to reconsider its plans for downtown. The move prompted both the Baton Rouge Area Chamber and Baton Rouge Area Foundation to issue statements in the project’s favor.
“Salt Lake City, Minneapolis and Seattle are among the cities that have recently built downtown libraries to frame their future,” BRAF President John Davies says. “The people of Baton Rouge also deserve such a place in downtown, a part of town that belongs to all residents.”
BRAC says the library, along with a controversial Galvez Plaza stage canopy for the North Boulevard Town Square, would help Baton Rouge attract jobs, investment and talent because “it will show citizens and visitors alike that we are a progressive, innovative region prepared to be successful in a 21st-century economy.”
Library supporters and detractors again filled the chamber, only to see Mayor Pro Tem Mike Walker dissolve the meeting for lack of a quorum. When a vote finally was taken Oct. 4, only two council members voted for the resolution to reconsider the library decision; three members who initially had backed the agenda item ended up voting against it.
“Some of the people who said they were against it, they folded and they voted for the thing,” says Mike Thibodeaux, president of the Baton Rouge Tea Party. “It’s a big disappointment.”
District 3 representative Chandler Loupe, who had voted against the new library in December and initially supported the recent reconsideration item, says he wanted the library board to look at options other than tearing down and rebuilding. But after speaking with the project architects, he discovered a feasibility study already had found a worthwhile renovation would have cost nearly $10 million.
“Looking at it from a cost-benefit standpoint, there wasn’t much difference between the rehab cost and what the new construction would be,” he says, adding that he didn’t think BRAC and BRAF had much impact on the final vote. Other members expressed reluctance to micromanage the library board’s decision.
Slater McKay is one of those young professionals who felt voters essentially had approved a new downtown library in 2005. McKay is president of the young-professionals group Forum 35; his stance on the library is his own, and not that of the organization.
“That library is a component of the whole downtown [renewal] process,” he says. “It has the potential to be a very important cog.”
McKay, who only recently became politically active, says he was surprised to discover how intently officials listened to his concerns, and how much residents can “move the needle.”
Bardwell, Loupe and District 9 representative Joel Boé say they don’t see any appetite from the council to revisit the library issue. But Bardwell says the council still has to sign off on the contracts to design and build the facility, which means council members still have two chances to inject themselves into the process.
“There are some possibilities of heading this thing off at the pass,” Thibodeaux says. “We’re not giving up completely.”
Depending on the length of opponents’ memories, he says, the downtown library might become an issue for the next tax renewal in 2015.
“Nobody wants to gut the library board’s budget,” Thibodeaux says. “On the other hand, we’d like to see the money better spent than this.”